A. Project Opportunity Description: |
A1. Project Name: |
Construction of the brick plant |
а. Short name: |
Bricks production |
b. Full name: |
The organization in |
c. Summary description: |
The main objective of the current project is to create modern brick plant for production of different types of quality bricks from the local raw resources. |
А2. Progress Status: |
Business-plan is available. The construction is coordinated with the municipal instances. Investor is required. |
А3. Organizations involved and their roles: |
1) |
А4. Project Description: |
The current project is aimed at the creation of modern brick plant for production of 30 million pieces per year. The concept of processing equipment and control system lets to produce a wide variety of bricks: faced brick, chipped brick, moulded brick and blocks for glue jointless laying. The proposed technology is flexible and doesn’t require large amounts of energy resources. The technology was tested and the high quality of products has been certified by competent structures in |
А4a. Project cost (mln USD): |
5.0 |
A5. Background / history / overall programme / related or similar projects: |
The actuality of the project is stressed by the fact that with the dissolution of the |
A6. Environmental impact summary: |
The proposed technology is friendly to the environment and does not have any hazardous wastes. |
A7. Possible obstacles/ problems/ risk assessment: |
The risk assessment for the project implementation is low. |
A8. Term of realization / term of recoupment (years): |
10 / 5,5 |
A9. Project’s branch: |
Construction materials production |
B. Capital Cost Items (additional requirements for project): |
|
B1. Project physical components |
B2. Capital cost (mln USD) |
Cost of building and assembly jobs |
0.3 |
Purchase of the equipment: |
4.2 |
Costs connected to the organization of the production: |
0.1 |
Current assets: |
0.4 |
Total: |
5.0 |
C. Capital Resources Available from Sponsors/ Proposers: |
|
C1. Resources 'in kind', grants, investments, equity / ownership, etc. |
C2. Amount (mln USD) |
Own funds: |
1.7 |
D. Required Financial Assistance: |
||
D1. Financing gaps, type of financial assistance required: |
||
Crediting. |
||
D2. Sources of finance |
D3. Type of investment |
D4. Amount (mln USD) |
Foreign investment funds: |
Credit: |
3.3 |
D5. Financial/ International Institution Name: |
E. Demand (users) and revenues: |
|
E1. Type of users/ markets, volumes, pricing, revenues, quantifiable benefits/ savings: |
|
Local and foreign construction enterprises and companies. lanned volume – 30 million bricks per year. Markets: the |
|
E2. Revenues (Sales) |
E3. Amount (mln USD) |
Incomes from sales: |
4.1 |
F. Operating and Maintenance Costs: |
|
F1. Cost components, strategies for cost recovery, operating organisations, subsidies, etc.: |
|
The enterprise is planned to be located on |
|
F2. Cost Item |
F3. Amount (mln USD) |
Total: |
2.3 |
G. Net Income Value: |
|
G1. Net Income Value |
G2. Amount (mln USD) |
Net profit: |
1.8 |
H. Project information source: |
H1. This form was completed by: |
Oleg Kondratovich, Head of Foreign Investment Department. |
H2. Organisation (address): |
|
H3. Тel/Fax/E-mail: |
Tel.: (+375-212) 21-09-27, fax: (+375-212) 26-08-02; e-mail: fez@vitebsk.by, www.fez-vitebsk.by |
H4. Date: |
June, 2009 |
H5. Supreme Organization: |
FEZ «Vitebsk» Administration |
项目资料由白俄罗斯驻中国使馆提供